How to Estimate as a Subcontractor: Pricing, Markup and Bid Mistakes

Home/Articles/How to Estimate as a Subcontractor: Pricing, Markup and Bid…

How to estimate as a subcontractor: step-by-step pricing, a worked example, markup, and the bid mistakes that cost subs jobs and money.

Get a Free Quote
Reviewed by Austin Smith, FounderUpdated November 4, 20267 min read
Quick AnswerTo estimate as a subcontractor, read your trade’s specification sections, take off quantities from the drawings, add waste, price materials from current quotes, convert quantities to labor hours with your production rates, add equipment, then add overhead and profit. Finish with clear inclusions, exclusions, alternates and unit prices, and acknowledge every addendum before you submit.

How to estimate as a subcontractor comes down to one rule: price the job you will actually build, not the job you see at a glance. Subs lose more money on missed scope and wrong labor assumptions than on material prices. This guide walks through the estimate step by step, with a worked example and the mistakes that cost subcontractors the most.

How this guide was prepared: written and reviewed by the Design Estimation estimating team, led by founder Austin Smith (7+ years in construction estimating) and backed by ASPE Certified Professional Estimators. Contract rules and rates vary by state and project.

Step-by-Step Subcontractor Estimate

  1. Read the bid documents: your trade’s specification sections, Division 01 general requirements, the bid form and every addendum.
  2. Take off quantities: measure and count everything in your scope, by area, floor or system.
  3. Add waste separately: keep net quantities and waste on different lines so both can be checked.
  4. Price materials: use dated supplier quotes, and include delivery, tax and escalation.
  5. Calculate labor: quantity divided by your production rate gives crew hours; multiply by your burdened labor rate.
  6. Add equipment: lifts, scaffolding, rentals, fuel and mobilization.
  7. Add lower-tier subs: any work you subcontract, with scope leveled.
  8. Add overhead, profit and contingency.
  9. Write the bid: inclusions, exclusions, qualifications, alternates and unit prices.
Request a Free Quote

Fill in your details and we’ll get back to you with a quote.

  • Quote reply within 1 hour
  • Estimates in 24–48 hours
  • Prepared by human estimators
Service
This field is required.
This field is required.
This field is required.

Worked Example: Pricing One Line of a Drawing Takeoff

The method is the same for every trade. Here it is with example rates; replace them with your own.

StepCalculation (example rates)Result
Net quantityFrom the takeoff10,000 sq ft
Waste+10%11,000 sq ft
Material11,000 × $0.60 per sq ft$6,600
Labor hours10,000 ÷ 40 sq ft per hour250 hours
Labor cost250 × $55 burdened rate$13,750
EquipmentLifts and scaffolding$1,200
Direct costMaterial + labor + equipment$21,550
Overhead (12%) and profit (10%)$21,550 × 1.12 × 1.10About $26,550

Labor is calculated from net quantity, not quantity with waste, because crews install the net area. Markup is applied after overhead; see markup vs. margin for why a 10% markup is not a 10% profit.

How Much Markup Should a Subcontractor Add?

There is no single rate. Overhead depends on company size, and profit depends on risk and market. Specialty trades often run higher net margins than general contractors, but small subs also carry higher overhead per dollar of work. Track your actual overhead as a percentage of revenue each year, then add profit on top; a bid that only covers overhead is a bid that only keeps your crews busy.

Estimating Mistakes That Cost Subcontractors Jobs and Money

MistakeFix
Pricing from the plans onlyRead your spec sections and Division 01
Waste hidden inside quantitiesShow waste on its own line
One production rate for everythingSplit quantities by height, access and complexity
Vague exclusionsList exactly what is not included
Missing an addendumTrack addenda on the bid form and update quantities
Old material pricesGet new quotes and note the quote date
No contingency on renovation workAdd contingency where conditions are unknown

When to Outsource the Takeoff

If you are bidding more jobs than your team can take off, outsourcing the quantities lets you spend your time on pricing and relationships. Our subcontractor estimating services deliver trade takeoffs in your format in 24 to 48 hours, and our guide to what a subcontractor is covers contracts, retainage and payment terms.

FAQ

Frequently Asked Questions

Quick answers about pricing subcontractor work.

  • How do subcontractors price a job?

    They take off quantities, price materials, convert quantities to labor hours, add equipment, then add overhead and profit. Inclusions and exclusions define what the price covers.

  • Should labor be calculated with waste included?

    No. Labor is usually based on net installed quantity, while material is based on quantity plus waste.

  • What should a subcontractor bid include?

    The price, scope inclusions and exclusions, alternates, unit prices, acknowledged addenda, schedule assumptions and bond or insurance status.

  • Why do subcontractor bids vary so much?

    Different scope assumptions, production rates, overhead and how much each sub wants the job. Clear exclusions make bids easier to compare.

  • Can someone else do my takeoff?

    Yes. Our human estimators prepare trade takeoffs in your format in 24 to 48 hours, with marked-up drawings so you can check every quantity.

Bid Deadline Coming Up?

Get a Bid-Ready Estimate in 24–48 Hours

Send your drawings and bid date. We'll confirm scope, price and delivery time before any work starts.