Articles · 8 min read

General Contractor Estimate Examples (Sample Estimates and Free Template)

Home/Articles/General Contractor Estimate Examples (Sample Estimates and …

General contractor estimate examples: a sample new house estimate by CSI division, a commercial build-out with line items, and a free estimate template.

Get a Free Quote
Design Estimation TeamUpdated October 21, 20268 min read
General Contractor Estimate Examples (Sample Estimates and Free Template)

There are two parts of the general contractor estimate: One is the summary which shows the cost of every trade by CSI division and then adds general conditions, overhead, profit, and contingency; and the other is the detail sheets which show each line item with quantity, unit and unit cost. Both a full summary for a new 2,400 sq ft house ($543,594, $226 per sq ft) and a commercial tenant build-out with line item detail are shown below.

A real estimate will give you the quickest insight into the way one is made. The following are general contractor estimates – these are simplified estimates (much like the sample provided) in the form that our general contractor estimation team uses when we estimate for our GC clients, and have sample prices included so that you understand the structure and the math. They are a guide, not a quote for your project – the price depends on the location and specification. See our full guide to construction cost estimation for a full detail of how estimates are constructed.

What a General Contractor Estimate Includes

SectionWhat it shows
Project informationProject name, address, drawing set and date, estimate date, estimator
Basis of estimateDrawings and specs used, addenda, assumptions, and the design stage
Summary by divisionTotal cost for each CSI division or trade
General conditionsSupervision, temporary facilities, cleanup, permits and insurance, priced from the schedule
MarkupsOverhead, profit, bonds, insurance and contingency, shown as separate lines
Detail sheetsLine items with quantities, units, unit costs, labor and material
Inclusions and exclusionsWhat the price covers and what it does not
Allowances and alternatesPlaceholder amounts for undecided items, and priced options

General Contractor Estimate Example 1: New 2,400 sq ft House

A new 2400 sq ft house on a slab foundation, wood frame, asphalt shingle roof, vinyl siding at front with brick veneer, mid-level finishes. Lot is level and clear, utilities are “at the street.

DivisionDescriptionCost
01General requirements (supervision, temp facilities, dumpsters, cleanup)$30,000
03Concrete (footings, foundation walls, slab, flatwork)$36,000
04Masonry (brick veneer at front elevation)$9,000
05Metals (steel beam, posts, lintels)$4,000
06Wood and plastics (framing, sheathing, trim, cabinets)$96,000
07Thermal and moisture (roofing, insulation, siding, sealants)$44,000
08Openings (windows, exterior and interior doors, hardware)$28,000
09Finishes (drywall, paint, flooring, tile)$56,000
10Specialties (bath accessories, mirrors, shelving)$3,500
11Equipment (appliance package)$9,000
12Furnishings (countertops, blinds)$12,000
22Plumbing$27,000
23HVAC$22,000
26Electrical and low voltage$25,000
31Earthwork (clearing, excavation, backfill, grading)$15,000
32Exterior improvements (driveway, walks, landscaping)$14,000
33Utilities (water, sewer, power service connections)$11,000
Subtotal, direct cost$441,500
Permits and fees$6,500
Overhead (8%)$35,840
Profit (7%)$33,869
Contingency (5%)$25,885
Total estimate$543,594
Cost per sq ftabout $226

Illustrative prices for a mid-range build. Land, design fees and financing are not included.

The key to notice is that wood framing and finishes make up the most significant costs, and that the MEP (plumbing, HVAC and electrical) cost is approximately 17%. These totals are one of the reasons for the huge range of numbers we have for our cost per square foot to build a house guide—just one example, change the finishes or the region, and the per-square-foot figure changes quickly.

General Contractor Estimate Example 2: 5,000 sq ft Office Build-Out

Interior tenant improvement to existing building – new partitions, two restrooms, new break room, new ceilings, new light fixtures, HVAC distribution and finishes. The base building shell, roof and main HVAC units are existing.

Detail Sheet: Framing, Drywall and Ceilings

Line itemQuantityUnitUnit costTotal
Metal stud partition, 3-5/8″ 25 ga at 16″ o.c.4,200sf wall$4.10$17,220
5/8″ Type X gypsum board, both sides, hung8,400sf$1.45$12,180
Tape and finish, Level 48,400sf$1.10$9,240
Sound attenuation batts in demising walls1,600sf$1.25$2,000
Acoustical ceiling tile 2×2 on suspended grid4,300sf$4.75$20,425
Gypsum board soffits and bulkheads260lf$38.00$9,880
Total$70,945

Unit costs include material and labor. Illustrative only.

Estimate Summary

DivisionDescriptionCost
01General conditions (10 weeks: superintendent, temp protection, cleanup, dumpsters)$58,000
02Selective demolition$14,000
06Millwork (reception desk, break room casework)$26,000
08Doors, frames, hardware and storefront glass$41,000
09Finishes: framing, drywall and ceilings (detail above)$70,945
09Finishes: flooring, base, paint, wall tile$57,000
10Specialties (signage, toilet accessories, fire extinguishers)$6,500
21Fire sprinkler modifications$16,000
22Plumbing (break room, two restrooms)$29,000
23HVAC (VAV boxes, ductwork, diffusers, controls)$62,000
26Electrical, lighting and data$68,000
Subtotal, direct cost$448,445
Builder’s risk and liability insurance (1.2%)$5,381
Overhead (6%)$27,230
Profit (5%)$24,053
Contingency (4%)$20,204
Total estimate$525,313
Cost per sq ftabout $105

Two things stand out on commercial estimates. First, general conditions are a real line priced from the schedule, not a rounded percentage: ten weeks of a superintendent is a known cost. Second, most of the dollars are subcontracted (HVAC, electrical, fire sprinkler, plumbing), so the quality of the GC estimate depends on how well those quotes are leveled against the scope.

Construction Estimate Template (Copy This Layout)

Whether you use a spreadsheet or estimating software, this structure works for almost any general contracting estimate:

ColumnWhat to enter
Division / cost codeCSI MasterFormat division and your internal cost code, such as 03 30 00 Cast-in-place concrete
DescriptionThe item of work, specific enough that someone else can price it
QuantityMeasured from the drawings, with waste noted separately
Unitcy, sf, lf, ea, ls, hr
Material unit costFrom a dated supplier quote
Labor hoursQuantity divided by production rate
Labor rateBurdened hourly rate
EquipmentRental or owned equipment cost for the item
SubcontractLeveled subcontractor price, if the item is subbed
TotalMaterial + labor + equipment + subcontract
Notes / sourceDrawing sheet, spec section, quote reference and assumptions

Below the line items, add rows for general conditions, overhead, profit, bonds, insurance and contingency, each shown separately so you can adjust them without touching the direct costs.

What a Construction Estimate Report Should Contain

When an estimate goes to an owner, lender or design team, it is usually sent as a report rather than a spreadsheet. A good construction estimate report includes:

  • A cover page with project, date, estimate type and design stage.
  • A one-page summary with totals by division and cost per square foot.
  • The basis of estimate: documents used, assumptions and pricing date.
  • Clear inclusions, exclusions, allowances and alternates.
  • Contingency and escalation, explained rather than buried.
  • Detail backup, if the recipient needs to review quantities.

Rough Estimate vs. Detailed Construction Estimate

A ballpark figure for the construction of a building is typically a square foot figure, such as 2,400 sq ft at a typical local cost per square foot, and with a wide range. It can be helpful in determining the action to take if you decide to move forward or not. A detailed estimate such as those listed above is created from a complete takeoff, and is the estimate you sign a contract on. We provide detailed information about the different types of construction cost estimates, including what they are and how accurate they are.

How to Tell if a Contractor Estimate Is Fair

  • It is itemized by division or trade, not a single lump sum.
  • Quantities and allowances are stated, so you can compare bids on the same basis.
  • Exclusions are clear. A low bid that excludes site work or permits is not really low.
  • Markups are reasonable for the project size and risk.
  • It is close to other bids for the same scope. A price far below the others usually means missed scope.
  • It matches a square foot sanity check for similar projects in your area.

Our article on what a construction estimate is lists the terms and conditions a contractor estimate should spell out.

From Estimate to Bid

Construction bid estimate occurs once the final numbers for subcontractors are included and once the contractor has applied markup to the bid based on market and client requirements and will submit a price on the bid form. Most changes will occur on bid day in the last few hours, as sub quotes are received. For bid-day strategy check our construction bid estimating guide.

Get a Complete Estimate for Your Project

Design Estimation creates complete general contractor estimates and trade takeoffs, broken down by CSI division and quantities, unit costs and a bottom line. Check out real full building estimate samples of GC work or submit estimates for 24-48 hours’ turnaround.

To get the bigger picture of the different types of estimates, the various ways to estimate costs, the expense of the estimate, and the typical pitfalls to avoid, check out our construction cost estimation guide.

Part of Our Complete Guide

This article is part of our complete guide to construction cost estimation, which covers the full process step by step.

Share This Entry

FAQ

Frequently Asked Questions

Quick answers to the questions contractors ask us most.

  • Why are there such differences in contractor bids?

    Differences in scope coverage, subcontractor pricing, markup and how busy each contractor is. When comparing bids, be sure to match each line to ensure bids are for the same work.

  • Let's take a look at the general contractors estimates.

    It provides a summary of costs per CSI division, general conditions, overhead, profit and contingency, with detailed line items. Line item quantity, unit, unit value and total value.

  • What is included in a contractor cost estimate?

    The material, labor, equipment, subcontractors, general conditions, overhead and profit & contingency. A good estimate also lists inclusions, exclusions, and allowances, and indicates the length of time the price will be available for.

  • What is the price of a new constructed house?

    Size, finishes, and location are the critical factors. The above sample 2,400 sq ft home before land, design and financing is approximately $543,594.

  • Do you have a free construction estimate template?

    Yes, the above column layout is a free template to be used in any spreadsheet. Each line item should be in a separate row, group rows by CSI division, and include markups as separate lines below direct costs.

  • What is the difference between a construction estimate and a construction bid?

    An estimate is the price that the work will cost the contractor and a bid is the price that will be put forward to the owner. The bid includes the numbers of the final subcontractors and the decisions on the contractor’s mark-up.

  • Contractor estimates – how accurate are they?

    The accuracy of the detailed estimate is around 5%-10% using complete drawings. The estimates of rough square feet may be in error by 20-30% or more.