Types of construction drawings and documents: disciplines, sheet numbers, plans, sections and details, SD to IFC sets, construction documents and BOQ vs BOM.

Get a Free Quote
Design Estimation TeamUpdated October 20, 20268 min read
Types of Construction Drawings and Documents (Plus BOQ vs. BOM)
Quick AnswerA set of construction drawings is organized by discipline: general (G), civil (C), landscape (L), structural (S), architectural (A), fire protection (F or FP), plumbing (P), mechanical (M) and electrical (E). Within each discipline you will find plans, elevations, sections, details and schedules. The drawings, the written specifications and the contract together make up the construction documents that a project is bid, permitted and built from.

Knowing how a drawing set is put together saves hours on every bid. This guide walks through the drawing types, how sheets are numbered, how a set changes from schematic design to issued for construction, and the other documents that sit alongside the drawings, including the difference between a bill of quantities and a bill of materials.

Drawing Disciplines and Sheet Designators

Most US drawing sets follow the US National CAD Standard, which assigns a letter to each discipline. The order below is the typical order of sheets in a set:

DesignatorDisciplineWhat it covers
GGeneralCover sheet, sheet index, code summary, life safety plans, general notes
CCivilGrading, drainage, utilities, paving and site layout
LLandscapePlanting, irrigation and hardscape
SStructuralFoundations, framing plans, beam and column schedules, connection details
AArchitecturalFloor plans, elevations, sections, wall types, door and finish schedules, details
IInteriorsInterior elevations, furniture and finish plans (on larger projects)
F / FPFire protectionSprinkler layouts, standpipes and fire pump details
PPlumbingWater, waste and vent layouts, risers, fixture schedules
MMechanicalHVAC duct and piping, equipment schedules, controls
EElectricalPower, lighting, one-line diagrams, panel schedules
TTelecommunicationsData, voice, security and audio-visual systems

How Construction Sheets Are Numbered

A sheet number such as A-201 tells you more than which page you are on. The letter is the discipline, the first digit is the sheet type, and the last digits are the sequence:

First digitSheet typeExample
0General: legends, notes, symbolsA-001
1PlansA-101 First floor plan
2ElevationsA-201 Exterior elevations
3SectionsA-301 Building sections
4Large-scale views (enlarged plans)A-401 Enlarged restroom plans
5DetailsA-501 Wall details
6Schedules and diagramsA-601 Door and finish schedules
93D representationsA-901 Isometric views

Sheet type designators per the US National CAD Standard. Many firms use their own variations.

The Main Types of Construction Drawings

  • Site plan: the building on its lot, with property lines, setbacks, parking, utilities and grading.
  • Floor plans: a horizontal cut through each level showing walls, doors, windows, rooms and dimensions.
  • Reflected ceiling plans (RCPs): the ceiling as if seen in a mirror on the floor, showing ceiling types, heights, lights and diffusers.
  • Roof plan: slopes, drains, curbs, rooftop equipment and roofing system.
  • Elevations: flat views of each exterior face, or interior walls, showing heights, materials and openings.
  • Sections: vertical cuts through the building or a wall, showing how the assembly goes together from foundation to roof.
  • Detail drawings: enlarged views of specific conditions, such as a window head, a parapet or a stair handrail, at scales like 1-1/2″ = 1′-0″.
  • Schedules: tables for doors, windows, finishes, hardware, equipment, fixtures and structural members.
  • Isometric drawings: 3D views, common for plumbing risers, ductwork and complex assemblies.
  • Structural drawings: foundation and framing plans, with beam, column and footing schedules and connection details.
  • MEP drawings: mechanical, electrical and plumbing layouts, risers and schedules.

For estimators, the schedules and details are where much of the money hides. A wall type that looks simple on the floor plan may turn out to be a two-hour rated assembly once you read the partition schedule.

Drawing Sets by Design Phase

A drawing set grows in detail as design progresses. Each stage is issued for a different purpose:

Phase / issueTypical completionPurpose
Schematic design (SD)About 15% to 30%Overall layout, massing and systems; early budget pricing
Design development (DD)About 50% to 65%Materials, systems and major dimensions fixed; more reliable estimates
Construction documents (CD)90% to 100%Full detail for permitting, bidding and construction
Permit setVariesSubmitted to the building department for plan review
Bid set100% CDs plus addendaThe documents contractors price
Issued for construction (IFC)FinalApproved for building, after permit comments and bid revisions
Conformed setFinalBid set updated to include all addenda, so the field works from one clean set
Record / as-built drawingsAfter completionWhat was actually built, including field changes

Completion percentages are typical ranges, not fixed rules.

The difference between schematic design and design development matters for pricing. An SD estimate is a budget built on square foot costs and assumptions. A DD estimate can be built from real quantities, but it still needs allowances for details that are not drawn yet.

What Are Construction Documents?

“Construction documents” means more than the drawings. A complete set usually includes:

DocumentWhat it is
DrawingsThe graphic description of the work, organized by discipline
Project manual / specificationsWritten requirements for materials, products, workmanship and procedures, organized by CSI MasterFormat division
Owner-contractor agreementThe contract itself, often an AIA A101 or similar
General and supplementary conditionsRights, responsibilities, payment, changes and claims, often AIA A201 plus project-specific changes
AddendaChanges and clarifications issued during bidding
Bid documentsInstructions to bidders, bid forms, bonds and alternates
ReportsGeotechnical, environmental and survey information, sometimes included for reference only

Construction Documents Through the Project Lifecycle

The document set keeps growing after the contract is signed. Here is what a typical project produces at each stage:

StageDocumentsPurpose
Design and biddingDrawings, specifications, contract and general conditions, bid forms, addenda, geotechnical and survey reportsDefine the work and the deal
PreconstructionPermits, baseline schedule, cost estimate and schedule of values, insurance and bonds, subcontractsPlan the work and set the budget
ConstructionRFIs, shop drawings and other submittals, change orders, daily logs, meeting minutes, inspection reports, pay applicationsTrack questions, changes, progress and payment
CloseoutAs-built drawings, O&M manuals, warranties, punch lists, lien waivers, certificate of occupancyHand over the building and close the contract

When drawings and specs conflict, the contract usually sets an order of precedence. A common rule is that specifications govern over drawings, and larger-scale details govern over smaller-scale plans, but the actual contract language is what counts.

BOQ vs. BOM: Bill of Quantities vs. Bill of Materials

Both are quantity lists, but they serve different purposes and audiences:

Bill of quantities (BOQ)Bill of materials (BOM)
What it listsItems of work with measured quantities and units, such as cubic yards of concrete or square feet of drywallThe specific materials and components needed to build or fabricate something
Who prepares itEstimator or quantity surveyor, usually for the owner or contractorFabricator, manufacturer, supplier or trade contractor
Main useTendering and pricing: every bidder prices the same quantitiesProcurement and fabrication: what to buy, cut or assemble
Includes labor?Priced rates usually include labor, materials and equipmentUsually materials only
Common whereUK, Middle East, Asia, Australia and international workManufacturing, fabrication and procurement everywhere

On most US projects, owners do not issue a formal BOQ. Each bidder does its own quantity takeoff, and the contractor later breaks the price into a schedule of values for billing. On international and public work, a BOQ is often part of the tender documents. Our guide to construction tender document preparation covers how BOQs and bid packages are put together.

How Estimators Read a Drawing Set

  • Start with the sheet index and general notes to confirm the set is complete and see which codes and standards apply.
  • Read the code summary for construction type, occupancy and sprinkler status, which drive rated assemblies.
  • Check the revision block and clouds on every sheet, and log all addenda.
  • Read schedules before measuring plans, so each wall, door and finish is priced as the right type.
  • Cross-check disciplines: architectural ceiling heights against mechanical duct sizes, structural openings against MEP penetrations.
  • Read the specs for products, testing and requirements that never appear on the drawings.

Help With Drawings and Takeoffs

Design Estimation prepares CAD drawings, as-built and shop drawings, and quantity takeoffs and estimates from full construction document sets for contractors across the US. See our CAD drawing services or send your drawing set for a quote.

Share This Entry

FAQ

Frequently Asked Questions

Quick answers to the questions contractors ask us most.

  • What are the types of construction drawings?

    The main types are site plans, floor plans, reflected ceiling plans, elevations, sections, details and schedules. These are produced for each discipline: civil, structural, architectural, mechanical, electrical, plumbing and fire protection.

  • What are construction documents?

    Construction documents are the drawings, specifications and contract documents that define a project. They include addenda and general conditions, and they are what contractors bid and build from.

  • What does IFC mean on drawings?

    IFC means “issued for construction.” It marks the drawing set approved for building, after permit comments and bid revisions have been incorporated.

  • What is a conformed set of drawings?

    A conformed set is the bid set updated to include all addenda and bid-phase changes. It gives the field one clean, current set instead of the original drawings plus separate addenda.

  • What is the difference between schematic design and design development?

    Schematic design sets the overall layout and concept; design development fixes materials, systems and major dimensions. SD supports budget pricing, while DD supports more detailed estimates.

  • What is a detail drawing in construction?

    A detail drawing is an enlarged view of a specific condition, such as a wall base, window head or connection. It shows exactly how materials meet, at a larger scale than the plans.

  • What is the difference between BOQ and BOM?

    A BOQ lists measured quantities of work for pricing; a BOM lists materials and components for purchasing or fabrication. BOQs are common in tenders outside the US, while BOMs are used by fabricators and suppliers everywhere.

  • What are building drawings?

    Building drawings are the plans, elevations, sections and details that describe a building for permits and construction. Our construction documentation services prepare these sets from sketches, PDFs or markups.