Labor is the biggest risk in a masonry bid. Material prices come from a supplier quote. Labor comes from your own judgment about how fast a crew will lay a wall, and a small miss on a large wall adds up fast.
This guide shows how masonry contractors figure labor cost per square foot for brick and block, using their own crew rates and production.
How this guide was prepared: Our estimators wrote this guide from the takeoffs we prepare for subcontractors across the US. Austin Smith, our founder, reviewed it. Our team holds ASPE CPE credentials.
Start With Your Crew’s Hourly Cost
A masonry crew is more than the mason. Add up everyone on the wall for one hour: masons, tenders, the mixer operator and the foreman’s share. Include wages, payroll taxes, insurance and benefits. This is your crew cost per hour. Use your own payroll numbers, not a national average, because rates change a lot from one city to the next.
Figure Production by Wall Type
Production is how much wall your crew finishes in an hour. It changes with the unit and the work:
- Brick veneer: a standard modular brick wall uses about 6.75 bricks per square foot, so the crew lays many small units for each square foot.
- CMU: a standard 8×16-inch block wall uses about 1.125 blocks per square foot, so the crew covers area faster but handles heavier units.
- Patterns and special units: soldier courses, rowlocks, arches and bullnose units all slow the crew down.
Track production on your own jobs. Have your foremen record the hours and the square feet of each wall type. After a few jobs, you will have real rates you can trust.
Do the Math
Divide your crew cost per hour by the square feet the crew lays per hour. That gives you labor cost per square foot for that wall type. Here is an example with made-up numbers only: if your crew costs $300 an hour and lays 50 square feet of plain CMU per hour, labor costs $6 per square foot. If the same crew lays 25 square feet of patterned brick per hour, labor costs $12 per square foot. Same crew, double the price.
You can also price brick labor per 1,000 units. Divide the crew cost per hour by the bricks laid per hour, then multiply by 1,000. Many masons think in this unit, so it helps to check your square foot price both ways.
What Raises Labor Cost
- Wall height: once the crew moves onto scaffolding, production drops. Price walls above scaffold height separately.
- Openings and corners: every window, door, pier and corner adds cuts and layout time.
- Grout and steel: fully grouted CMU walls with many bars take longer than partly grouted walls.
- Weather: cold weather work in places like Chicago or Denver needs enclosures and heat, and crews lay less per hour.
- Access: tight sites, occupied buildings and long material carries slow everything down.
Labor Items That Are Easy to Miss
- Scaffold erection, moves and removal.
- Installing flashing, weeps, ties and joint reinforcement.
- Setting lintels and building bond beams.
- Cleaning down the wall at the end.
- Mockup panels when the spec calls for them.
Check Your Rate Before You Bid
Compare your labor cost per square foot against past jobs with similar walls. If the number is far below what you usually see, look for a wall type or height you priced at the wrong rate. Our brick cost guide covers the material side of the same wall.
Get Quantities by Wall Type
Labor rates only work when the quantities are split the right way. Our masonry estimating services break out brick, block, grout and steel by wall type and height, so you can apply your own labor rates line by line.
Frequently Asked Questions
Quick answers for subcontractors pricing this work.
How do you calculate masonry labor cost per square foot?
Divide your crew’s total hourly cost by the square feet of wall the crew lays per hour. Do this for each wall type and height.
Why does brick cost more labor than block per square foot?
A brick wall uses about 6.75 units per square foot, while CMU uses about 1.125. The crew handles far more units for the same area.
How do you price brick labor per 1,000?
Divide your crew cost per hour by the bricks laid per hour, then multiply by 1,000.
What raises masonry labor cost?
Wall height, openings, corners, patterns, grouting, cold weather and tight access.
Related Articles
Articles · 15 min readStucco Cost Estimator and Calculator: Price per Square Foot (2026-27)Read Article →
Articles · 7 min readBrick Sizes and Dimensions Chart (US, UK, Australia) + Bricks per Square FootRead Article →
Articles · 10 min readCost per Square Foot to Build a House: 2026-27 Numbers and BreakdownRead Article →
Articles · 13 min readMasonry Repair Cost: Guide to Brick and Stone PricingRead Article →
Articles · 2 min readLVP Flooring Installation Cost Calculator: How to Price LVP JobsRead Article →
Articles · 12 min readBrick Cost Estimator 2026-27: Brick Wall & Patio Cost Calculator USARead Article →Get a Bid-Ready Estimate in 24–48 Hours
Send your drawings and bid date. We'll confirm scope, price and delivery time before any work starts.