Articles · 5 min read

Excavation Production Rates: How to Price Equipment by the Cubic Yard

Home/Articles/Excavation Production Rates: How to Price Equipment by the C…

How sitework subs turn machine output into a cost per cubic yard, with a worked example and the factors that slow production down.

Get a Free Quote
Reviewed by Austin Smith, FounderUpdated November 20, 20265 min read
Quick AnswerTo price excavation by the cubic yard, figure how many bank cubic yards your machine moves per hour, then divide the hourly cost of the machine, operator and support crew by that number. Adjust the production rate for soil, depth, swing, truck wait time and job efficiency.

Excavation bids live and die on production rates. Two contractors can measure the same cut and fill and still be far apart on price, because one assumes the machine moves twice as much dirt per hour as the other.

This guide shows you how to use production rates to price equipment by the cubic yard.

How this guide was prepared: Our estimators wrote this guide from the takeoffs we prepare for subcontractors across the US. Austin Smith, our founder, reviewed it. Our team holds ASPE CPE credentials.

What a Production Rate Is

A production rate is how much material a machine moves in an hour, usually in bank cubic yards. It depends on the bucket size, the soil, the cycle time and how well the job runs. Manufacturer handbooks give ideal numbers. Real jobs rarely hit them, so you need to adjust.

Bucket Size and Cycle Time

Start with the bucket. A full bucket rarely holds its rated size, so apply a fill factor based on the soil. Loose sand fills well.

Wet clay and rocky soil do not. Then figure the cycle time: dig, swing, dump and return. More swing and deeper digs mean longer cycles and fewer buckets per hour.

Job Efficiency

No crew works a full 60 minutes every hour. Operators wait for trucks, move the machine and stop for grade checks. Most estimators use an efficiency factor to reflect real working time. Base it on your own job records whenever you can.

A Worked Example

Here is how the math works, using example numbers only. Say your excavator, operator, fuel and a laborer cost $250 an hour together. After fill factor, cycle time and efficiency, you expect it to move 100 bank cubic yards per hour.

Your excavation cost is $250 divided by 100, or $2.50 per bank cubic yard. If the soil turns out to be wet clay and production drops to 70 yards per hour, the cost rises to about $3.57 per yard. That is why soil conditions matter so much.

Do Not Forget Trucking

If the dirt leaves the site, trucking often costs more than digging. Convert bank yards to loose yards with a swell factor, then figure how many truckloads you need. Truck cycle time depends on haul distance, traffic and dump wait times. Make sure you have enough trucks so the excavator never sits idle.

What Slows Production Down

  • Rock, cobbles and hard caliche.
  • Groundwater and rain.
  • Tight sites with little room to swing or stage trucks.
  • Deep trenches that need shoring or trench boxes.
  • Working around existing utilities.

Bank, Loose and Compacted Yards

Dirt changes volume as you move it. Soil in the ground is measured in bank cubic yards. When you dig it, it swells and becomes loose cubic yards.

When you place and compact it, it shrinks into compacted cubic yards. Each soil type swells and shrinks by a different amount, so check the geotechnical report.

Keep your units straight. Price digging in bank yards, trucking in loose yards and fill placement in compacted yards. Mixing these up is one of the fastest ways to miss an earthwork bid.

Match the Fleet

Your excavator only produces as fast as the trucks can haul. If the excavator can load a truck every few minutes but trucks come back less often, the machine sits and waits. Figure the truck cycle time (load, haul, dump and return) and add trucks until the excavator works steadily.

The same idea applies to dozers spreading fill and rollers compacting it. The slowest machine sets the pace for the whole crew.

Read the Geotechnical Report

The geotechnical report tells you what is in the ground. Look for rock depth, groundwater depth, soil types and any notes about unsuitable soil. If the borings show rock at 6 feet and your excavation goes to 10 feet, you need a separate production rate, and maybe a breaker or blasting, for the rock. If the report shows groundwater, plan for dewatering.

If there is no geotech report, say so in your bid and state the soil you assumed. That protects you if the site turns out harder than expected.

Track Your Own Production

The most reliable production rates are the ones you record on your own jobs. Have your foremen log the hours each machine works and the yards it moves. After a few jobs, you will know your real rates in your local soils. Those numbers beat any handbook.

Get Help With Earthwork Quantities

Production rates only work if the quantities are right. Our earthwork and sitework estimating services measure cut, fill and trench volumes from the grading plans, so you can apply your own rates with confidence.

Share This Entry

FAQ

Frequently Asked Questions

Quick answers about excavation pricing for subcontractors.

  • What is an excavation production rate?

    It is how much material a machine moves per hour, usually measured in bank cubic yards.

  • How do you price excavation per cubic yard?

    Divide the hourly cost of the machine, operator and crew by the cubic yards moved per hour. Then add trucking, disposal, overhead and profit.

  • Why are real production rates lower than handbook rates?

    Handbook rates assume ideal conditions. Real jobs lose time to soil, weather, truck waits and moving the machine.

  • Does trucking cost more than digging?

    Often, yes, when the dirt leaves the site. Haul distance and truck wait times drive the cost.