Articles · 8 min read

Rebar in Footings, Slabs and Stirrups: Spacing, Layout and Bar Bending Schedules

Home/Articles/Rebar in Footings, Slabs and Stirrups: Spacing, Layout and …

Footing rebar, slab rebar spacing and stirrups explained: ACI cover rules, typical layouts, stirrup cut length, bar bending schedules and worked takeoffs.

Get a Free Quote
Design Estimation TeamUpdated October 19, 20268 min read
Quick AnswerMost residential footings use two continuous #4 bars near the bottom, held 3″ above the soil. Slabs on grade typically use #3 or #4 bars at 12″ to 18″ on center each way, supported in the middle to upper third of the slab. Beam stirrups are usually #3 or #4 closed ties, spaced closer near the supports where shear is highest. The structural drawings always govern; these are the starting points estimators and field crews see most often.

This guide covers where rebar goes in footings, slabs and beams, the cover and spacing rules behind those layouts, and how a bar bending schedule turns all of it into a list a fabricator can cut and bend. It picks up where our rebar size chart leaves off.

Concrete Cover: How Far Rebar Sits From the Surface

Cover is the concrete between the rebar and the outside face. It protects the steel from corrosion and fire and lets the bar bond to the concrete. Too little cover is one of the most common inspection failures. ACI 318 sets these minimums for cast-in-place concrete:

ConditionMinimum cover
Cast against and permanently exposed to earth (footings, grade beams)3″
Exposed to earth or weather, #6 to #18 bars2″
Exposed to earth or weather, #5 bars and smaller1-1/2″
Not exposed: slabs, walls and joists, #11 and smaller3/4″
Not exposed: beams and columns (to ties and stirrups)1-1/2″

Minimum specified cover per ACI 318 for non-prestressed cast-in-place concrete. Project specifications may require more.

For estimating, cover matters because it shortens every bar. A 3″ cover on each end of a footing bar takes 6″ off its length, and on a large foundation that adds up to real tonnage.

Rebar in Footings

Continuous (strip) footings under walls carry the building load and bridge soft spots in the soil. Their reinforcement is simple, but the details are where takeoffs go wrong.

  • Longitudinal bars: commonly two #4 or #5 bars running the length of the footing, 3″ clear of the bottom and sides.
  • Transverse bars: wider footings and spread footings under columns get bars in both directions, forming a mat.
  • Corner and intersection bars: L-shaped bars lap the longitudinal bars at corners and tees so the reinforcement stays continuous. These are easy to miss in a takeoff.
  • Dowels: vertical bars hooked into the footing and extending up into the stem wall or CMU wall, tying the two together.
  • Laps: wherever a bar run is longer than the stock length.

In higher seismic design categories, the International Residential Code requires reinforcement in footings and stem walls, and many engineers specify continuous bars even where the code does not. If a plan set shows “2-#4 cont.” in a footing section, that note applies to every foot of that footing type on the foundation plan.

Supporting Rebar in a Footing

Bars must be supported at the correct height before the pour, not pulled up into the concrete during placement. Use concrete blocks (dobies) or rebar chairs rated for the load. Bricks, wood scraps and rocks are common on residential sites and are often rejected by inspectors because they can crack, rot or wick moisture to the steel.

Rebar Spacing for Concrete Slabs

Slab reinforcement does two jobs: it controls cracking from shrinkage and temperature changes, and in structural slabs it carries bending loads. Typical layouts:

Slab typeCommon reinforcementNotes
Residential slab on grade#3 or #4 at 12″ to 18″ o.c. each waySome slabs use welded wire or fibers instead; check the drawings
Driveway or patio#3 or #4 at 18″ o.c. each wayThicker at the apron where trucks turn
Garage or shop slab#4 at 12″ to 18″ o.c. each wayHeavier loads, often thicker slab
Commercial slab on grade#4 or #5 at 12″ to 18″ o.c. each wayOften with thickened edges and added bars at joints
Structural (suspended) slabDesigned by the engineerTop and bottom mats, extra bars over supports

Typical layouts only. Bar size and spacing are set by the structural drawings.

ACI 318 also caps spacing. For shrinkage and temperature reinforcement, bars can be no farther apart than 5 times the slab thickness or 18 inches, whichever is less. For main flexural bars in structural slabs, the limit is 3 times the slab thickness or 18 inches.

Where Rebar Sits in a Slab

Rebar lying on the subgrade does almost nothing. For a slab on grade, bars should sit in the middle to upper third of the slab depth, on chairs spaced closely enough that crews walking on the mat do not push it down. In a 4″ slab, that usually means about 1-1/2″ to 2″ below the top surface. “Hooking” the mesh up during the pour is unreliable and is a common cause of cracked slabs.

Rebar Stirrups: What They Are and How to Size Them

Stirrups are bent bars that wrap around the main longitudinal bars in a beam. They resist shear and hold the main bars in position. In columns, the same shapes are called ties and they keep the vertical bars from buckling.

  • Common sizes: #3 for most beams, #4 for larger or heavily loaded beams.
  • Shapes: closed rectangular stirrups, open U-stirrups with a separate cap tie, and multi-leg stirrups for wide beams.
  • Hooks: seismic designs use 135-degree hooks that wrap back into the beam core. Non-seismic designs may allow 90-degree hooks.
  • Spacing: closest near the supports, where shear is highest, and wider toward midspan. Where shear reinforcement is required, ACI 318 generally limits spacing to half the beam’s effective depth or 24 inches.

Types of Stirrups

TypeShapeWhere used
Two-legged closed stirrupRectangle closed with 135-degree hooksMost beams; required where torsion or seismic detailing applies
Open U-stirrup with cap tieU shape closed by a separate top barBeams cast with a slab, where top bars go in later
Multi-leg (four-legged) stirrupTwo overlapping closed stirrups, or a closed stirrup plus crosstiesWide beams and beams with high shear
Single-leg crosstieStraight bar with a 135-degree hook at one end and a 90-degree hook at the otherRestraining intermediate bars in wide beams and columns
Spiral or circular tieContinuous helix or circular hoopsRound columns, piles and drilled shafts
Rectangular or diamond column tieClosed tie, sometimes diamond-shaped around inner barsRectangular and square columns

Estimating Stirrup Cut Length

A stirrup’s cut length is its perimeter inside the cover plus an allowance for the hooks. For estimating, a practical approach is:

Cut length = 2 x (width – 2 x cover) + 2 x (depth – 2 x cover) + 2 x hook allowance

For a 135-degree hook, an allowance of about 10 bar diameters per hook is a common estimating figure. Fabricators use exact bend deductions from their equipment, so treat this as a takeoff number, not a shop number.

Worked Example 1: Footing Rebar Takeoff

A house foundation with 150 lf of continuous footing, reinforced with 2 #4 bars continuous, 20 ft stock bars, 24″ laps, corner bars at four corners and #4 dowels at 48″ on center into the stem wall (about 3 ft per dowel including the hook).

Line itemCalculationQuantity
Continuous bars2 bars x 150 lf300 lf
Lap splices2 bars x 8 laps x 2 ft32 lf
Corner bars4 corners x 2 bars x 4 ft32 lf
Dowels150 lf / 4 ft = 38 dowels x 3 ft114 lf
Total #4Sum of the above478 lf
Weightx 0.668 lb/ft319 lb
With 5% wastex 1.05about 335 lb

Corner bars and dowels make up almost a third of the total here. Leaving them out is the single most common footing takeoff error we see.

Worked Example 2: Stirrups for a Concrete Beam

A 12″ x 18″ beam, 20 ft long, with #3 closed stirrups at 8″ on center, 1-1/2″ cover and 135-degree hooks.

Line itemCalculationQuantity
Inside dimensions12″ – 3″ by 18″ – 3″9″ x 15″
Perimeter2 x (9″ + 15″)48″
Hook allowance2 hooks x 10 x 0.375″7.5″
Cut length per stirrupPerimeter + hooks55.5″ (about 4.62 ft)
Number of stirrups(240″ / 8″) + 131 stirrups
Total #331 x cut lengthabout 143 lf
Weightx 0.376 lb/ftabout 54 lb

Real beams rarely use one spacing for the full length. A typical schedule might call for the first stirrup at 2″ from the face of support, then a tighter spacing for a set distance, then a wider spacing through the middle. Count each zone separately.

Bar Bending Schedules (BBS)

A bar bending schedule lists every bar a fabricator has to cut and bend. It is the bridge between the structural drawings and the shop, and it is also the most accurate basis for a rebar estimate. A typical BBS includes:

ColumnWhat it shows
Bar markA unique ID that matches tags on the bundles and the placing drawings
Member / locationFooting F1, beam B3, slab grid C-D, and so on
Bar size and gradeFor example #4 Grade 60
Shape codeA standard bend type (US fabricators use CRSI shape codes)
Bend dimensionsThe leg lengths for each bend
Number of barsQuantity of that mark
Cut lengthTotal length of each bar before bending
Total weightNumber x cut length x weight per foot

On commercial work, the BBS usually comes with rebar shop drawings (placing drawings) that show crews where every mark goes. Errors in either document mean bars that do not fit, re-bending in the field, or a delayed pour.

Common Footing and Slab Rebar Mistakes

  • Rebar lying on the ground instead of on chairs or dobies.
  • Missing corner bars and dowels in footing takeoffs.
  • Ignoring cover, so every bar in the estimate is too long.
  • One spacing for the whole beam when the schedule has tighter end zones.
  • Forgetting “top and bottom” or “each way” notes that double the quantity.
  • No laps at construction joints where the pour sequence breaks a run.
  • Accessories left out: chairs, bolsters, dobies and tie wire are small per piece but add up on a large slab.

Reinforced CMU walls carry their own rules for grouted cells and bond beams. Our CMU block sizes and estimating guide covers grout and reinforcement in block walls.

Get a Rebar Takeoff or Bar Bending Schedule

Design Estimation prepares rebar takeoffs, bar bending schedules and placing drawings for contractors, concrete subcontractors and fabricators across the US, with quantities by element and bar mark. Turnaround is typically 24 to 48 hours. See our rebar estimating services or send your structural drawings for a quote.

Share This Entry

FAQ

Frequently Asked Questions

Quick answers to the questions contractors ask us most.

  • How much rebar goes in a footing?

    Most residential continuous footings use two #4 bars running the full length. Larger or more heavily loaded footings may use #5 bars or bars in both directions. Corner bars and dowels into the wall are extra and must be counted too.

  • How far should rebar be from the bottom of a footing?

    Rebar in footings cast against soil needs at least 3″ of concrete cover. Support the bars on concrete dobies or chairs so they stay at that height during the pour.

  • What is the standard rebar spacing for a concrete slab?

    Residential slabs commonly use #3 or #4 bars at 12″ to 18″ on center each way. ACI 318 limits shrinkage and temperature bar spacing to 5 times the slab thickness or 18″, whichever is less.

  • Where should rebar be placed in a slab on grade?

    In the middle to upper third of the slab, never on the subgrade. In a 4″ slab that is roughly 1-1/2″ to 2″ below the surface, supported on chairs.

  • What are stirrups in concrete?

    Stirrups are bent bars that wrap around a beam’s main reinforcement. They resist shear forces and hold the main bars in place. In columns, the same closed shapes are called ties.

  • What size rebar is used for stirrups?

    #3 bars are the most common stirrup size, with #4 used in larger beams. Spacing is tightest near supports, where shear is highest.

  • What is a bar bending schedule?

    A bar bending schedule (BBS) lists every bar to be cut and bent, with its mark, size, shape, length, quantity and weight. Fabricators work from it, and it gives the most accurate rebar tonnage for an estimate.

Bid Deadline Coming Up?

Get a Bid-Ready Estimate in 24–48 Hours

Send your drawings and bid date. We'll confirm scope, price and delivery time before any work starts.

Scroll to Top