At Design Estimation, we prioritize transparency and trust in every project. To give you confidence in our electrical estimation services, we’re sharing a clear overview of our process, along with a sample to illustrate how we work. Here’s how we ensure you get accurate and reliable estimates for your electrical projects.
Why Trust Us?
Our process is designed to be transparent, efficient, and client focused. By providing clear communication at every step and a detailed breakdown of costs, we ensure you have full confidence in our services. Want an estimate like this for your next bid? Send us your drawings and we will deliver an itemized electrical estimate in the same format.
Electrical Estimate Sample at a Glance
| Project | Commercial quick-service restaurant with drive-thru, Winchester, California |
|---|---|
| Scope | CSI Division 26 – Electrical (plus Division 01 general requirements) |
| Line items | 123 |
| Material cost | $152,893 |
| Labor cost | $193,405 (2,035 man-hours at a $82.17/hr crew rate) |
| Direct cost | $346,298 |
| Markups | Overhead 15%, profit 10%, insurance 4%, contingency 4%, sales tax on materials |
| Total bid | $472,426 |
Labor accounts for roughly 56% of direct cost on this project, which is typical for commercial electrical work with long branch-circuit conduit runs. That ratio is one reason a detailed electrical estimating service pays for itself: small errors in labor units multiply quickly across thousands of feet of conduit and wire.
Fill in your details and we’ll get back to you with a quote.
- Quote reply within 1 hour
- Estimates in 24–48 hours
- Prepared by human estimators
What's Included in This Electrical Estimate
The estimate follows the drawing set system by system, so you can check every number against the plans. Here is what each section covers.
| Section | Items | What’s priced |
|---|---|---|
| General requirements (Div. 01) | 1 | Site supervision, final cleanup, dumpster |
| Lighting fixtures | 19 | Each fixture type by plan tag, manufacturer and catalog number: site lights, troffers, downlights, pendants, exit and emergency lighting |
| Power items | 35 | Receptacles (GFCI, WP, isolated ground, USB), junction boxes, disconnects, motor starters, EV charger, UL 924 transfer devices, emergency inverters |
| Conduit & wire | 31 | Conduit by size and type (EMT, PVC, underground) and wire by gauge, including grounding, Cat 5 and communication cable, with 10% wastage |
| Switches, sensors & controls | 6 | Single-pole and dimming switches, vacancy and occupancy sensors, daylight-zone dimming controllers |
| Communication & security | 3 | Telecom outlets, telephone cabinet with plywood backboard, security cameras |
| Service & riser | 8 | Pad-mount transformer (install only), meter socket, service conductors, main disconnects |
| Switchboard & panels | 6 | 600A main switchboard (65kAIC, 208/120V, 3-phase, 4-wire) and five branch panels |
| Circuit breakers | 14 | Breakers by amperage and pole count, including 157 single-pole 20A breakers |
Some of the larger takeoff quantities give a sense of scale: 9,350 LF of 3/4″ conduit and 17,741 LF of #12 wire after wastage, along with 60 standard duplex receptacles and 63 junction boxes.
How to Read an Electrical Estimate
Every line item in the sample uses the same columns. Once you know what each one means, you can audit any estimate in minutes.
- Description and CSI section. The item as shown on the drawings, with the fixture tag (for example, “14A”) so you can find it on the lighting plan.
- Unit of measure. EA (each) for devices and fixtures, LF (linear feet) for conduit and wire, LS (lump sum) for general requirements.
- Quantity, wastage and quantity with wastage. We add 10% to conduit and wire for cut-offs, bends and terminations. Devices are counted exactly, with 0% wastage.
- Unit and total material cost. Current supplier pricing for the specified product, not a generic allowance.
- Total man-hours. Labor units multiplied by quantity. In this sample a duplex receptacle carries about 0.6 hours and a 2×2 LED troffer about 1.6 hours.
- Crew rate and labor cost. A blended hourly rate for the crew, multiplied by man-hours. Rates are set for the project’s location.
- Total item cost. Material plus labor for that line, rolled up into the trade total.
Markup summary from the sample: Direct cost $346,298 + overhead (15%) $51,945 + profit (10%) $34,630 + insurance (4%) $13,852 + sales tax on materials $11,849 + contingency (4%) $13,852 = $472,426 total bid.
We set markups to match your company’s numbers. Tell us your overhead, profit and insurance rates and the estimate arrives bid-ready.
Sample Line Items From the Electrical Estimate
Here is an excerpt of ten line items exactly as they appear in the full sample, so you can see the level of detail without opening the PDF. Every line carries its own quantity, wastage, material cost, man-hours and labor cost at the $82.17 per hour crew rate.
| Description | Unit | Qty | Qty with waste | Material | Man-hours | Labor | Item total |
|---|---|---|---|---|---|---|---|
| Duplex receptacle | EA | 60 | 60 | $2,970 | 35.82 | $2,943 | $5,913 |
| Duplex receptacle, GFCI / weatherproof | EA | 6 | 6 | $408 | 3.80 | $312 | $720 |
| 2×2 recessed LED flat panel troffer | EA | 30 | 30 | $3,960 | 47.97 | $3,942 | $7,902 |
| Line voltage dual technology occupancy sensor | EA | 2 | 2 | $210 | 2.29 | $188 | $398 |
| 3/4″ conduit | LF | 8,500 | 9,350 | $18,139 | 579.70 | $47,632 | $65,771 |
| #12 wire | LF | 16,128 | 17,741 | $4,258 | 124.18 | $10,204 | $14,462 |
| Panel A, 225A, 208/120V, 3P, 4W, 65kAIC | EA | 1 | 1 | $1,250 | 10.75 | $883 | $2,133 |
| Main switchboard, 600A, 208/120V, 3PH, 4W, 65kAIC | EA | 1 | 1 | $9,575 | 28.58 | $2,348 | $11,923 |
| 600A/3P disconnect switch | EA | 1 | 1 | $3,072 | 3.76 | $309 | $3,381 |
| 60A/3P disconnect switch | EA | 1 | 1 | $320 | 1.28 | $106 | $426 |
Excerpt from the full 123-line sample. Conduit and wire carry 10% wastage; devices and equipment are counted exactly.
Notice where the money is: the 3/4″ conduit line alone is about $65,800, most of it labor. On commercial electrical bids, branch conduit and wire usually drive the labor total, which is why measuring runs accurately matters more than pricing devices to the penny.
Electrical Labor Units Used in This Sample
Labor units are the hours it takes to install one unit of an item. These are the units behind the sample, calculated from its man-hours and quantities:
| Item | Labor unit |
|---|---|
| Duplex receptacle | About 0.60 hours each |
| GFCI / weatherproof receptacle | About 0.63 hours each |
| 2×2 LED troffer | About 1.60 hours each |
| Occupancy sensor | About 1.15 hours each |
| 3/4″ conduit | About 6.2 hours per 100 LF |
| #12 wire | About 0.7 hours per 100 LF |
| 225A branch panel | About 10.75 hours each |
| 600A main switchboard | About 28.6 hours each |
| 60A/3P disconnect | About 1.3 hours each |
Units reflect this project’s conditions. Adjust for ceiling height, building type, access and your crew’s own production history.
How to Write an Electrical Estimate
- Review the electrical set and specs. Read the lighting and power plans, panel schedules, riser diagram, fixture schedule and Division 26 specifications. Note anything that is by others, such as utility work or low voltage.
- Count devices and fixtures. Count every receptacle, switch, sensor and fixture by type and plan tag.
- Measure conduit and wire. Measure branch and feeder runs by size, then add wastage, typically about 10% for cut-offs, bends and terminations.
- Price materials. Use current supplier pricing for the specified products, including the switchboard, panels and breakers from the schedules.
- Apply labor units. Multiply each quantity by its labor unit to get man-hours, then multiply by a crew rate set for the project location.
- Add general requirements and markups. Supervision, cleanup, overhead, profit, insurance, sales tax on materials and contingency.
- Check the totals. Compare cost per square foot and labor share against similar jobs before you submit.
For the same process applied to every trade, see our guide to construction estimating for beginners.
Electrical Estimate Template
You can rebuild the format of this sample in any spreadsheet. Use one row per item and these columns:
| Column | What to enter |
|---|---|
| Item no. and description | The item as shown on the drawings, with the fixture or panel tag |
| CSI section | For example 26 05 33 for raceways or 26 24 16 for panelboards |
| Unit | EA, LF or LS |
| Quantity | Counted or measured from the plans |
| Wastage % and quantity with wastage | About 10% on conduit and wire, 0% on devices |
| Unit material cost and total material | From a dated supplier quote |
| Labor unit and total man-hours | Hours per unit times quantity |
| Crew rate and total labor | Blended hourly rate for the project location |
| Item total | Material plus labor |
Below the line items, add rows for overhead, profit, insurance, sales tax and contingency, exactly as the markup summary above does. When you send the price to a client, wrap it in a proposal that lists inclusions, exclusions, allowances, how long the price is valid and payment terms. Our article on what a construction estimate should include covers those terms, and our general contractor estimate examples show how electrical rolls into a full project estimate.
Residential vs. Commercial Electrical Estimates
- Residential estimates are often priced per device or per opening, with Romex wiring, a single service panel and a short line-item list.
- Commercial estimates, like this sample, price conduit and wire by the foot, carry switchboards, multiple panels, emergency lighting and controls, and run to over a hundred line items.
- Both use the same logic: measured quantities, material pricing, labor units and markups.
Our Electrical Estimating Process
- Send your drawings. Upload electrical plans, the panel schedules, the riser diagram, and specifications through our contact page.
- Scope review. An estimator confirms scope, exclusions and bid date. Any gaps between the drawings and specs are flagged early. For GC bids, we can add a full constructability review and scope gap analysis.
- Takeoff and pricing. Every device, fixture, run of conduit and panel is counted, measured and priced with local material costs and labor rates.
- Delivery in 24–48 hours. You receive an itemized estimate in the format shown in this sample, ready to review, adjust and submit.
Who Uses Our Electrical Estimates
Electrical subcontractors use them to bid more projects without adding in-house estimators. Our subcontractor estimating services cover every trade you might self-perform. General contractors use them to check sub bids and build complete budgets through our general contractor services. Owners and developers use them to set realistic budgets before going to bid.
Electrical is rarely priced alone. We also estimate the rest of the MEP package: mechanical, plumbing, and fire protection. Once you win the job, our shop drawing services and BIM coordination carry the project into construction.
Estimates Priced for Your Market
This sample is priced for Southern California. We adjust labor rates, material pricing and sales tax for wherever you build, including California, Texas, Florida, New York, and every other state on our service areas page.
More Estimate Samples
- Mechanical estimation samples: HVAC equipment, ductwork and piping
- USA project samples: estimates across trades and building types
- All projects: US, Canadian and Australian work
Share This Entry
Frequently Asked Questions
Quick answers to the questions contractors ask us most.
What does an electrical estimate include?
A complete electrical estimate includes itemized quantities, material costs, labor hours and markups for every system on the drawings. That covers lighting, power devices, conduit and wire, panels, breakers, service equipment, low voltage and controls, organized so each line can be checked against the plans.
How are labor hours calculated in an electrical estimate?
Labor hours are calculated by multiplying a labor unit for each item by its quantity. For example, about 0.6 hours per duplex receptacle or 1.6 hours per 2×2 troffer. Total hours are then multiplied by a local crew rate to get labor cost.
How long does an electrical estimate take?
Most electrical estimates are delivered within 24–48 hours of receiving complete drawings. Very large or multi-building projects may take longer, and we confirm the delivery date before starting.
What drawings do you need for an electrical takeoff?
Send the electrical plans, lighting and power layouts, panel schedules, riser diagram, and specifications. Fixture schedules and site plans help us capture site lighting and underground conduit accurately.
Can you use my company's markups and labor rates?
Yes. We apply your overhead, profit, insurance and crew rates so the estimate is ready to submit. If you don’t provide them, we use typical rates for the project’s location and label every assumption.
Is there a free electrical estimate template?
Yes, the column layout above works as a free electrical estimate template in any spreadsheet. List each item with unit, quantity, wastage, material, labor units and crew rate, then add markups below the line items.
What labor units are used in electrical estimating?
Labor units are hours per item, such as about 0.6 hours per duplex receptacle or about 6 hours per 100 LF of 3/4″ conduit in this sample. Many contractors start from published labor unit manuals and adjust them with their own job history.
Can I download this electrical estimate sample?
Yes, the full 123-line sample is available as a PDF on this page. It shows every line item, man-hour and markup for a commercial restaurant project in California.
Do you estimate other trades besides electrical?
Yes. We estimate all CSI divisions, including mechanical, plumbing, fire protection, concrete, framing, roofing and finishes. See our full list of estimating services or browse the general FAQ.
Related Articles
Articles · 2 min readRoofing Weatherproofing Estimation SamplesRead Article →
Articles · 2 min readFinishing Carpentry Estimation SamplesRead Article →
Articles · 4 min readMechanical Estimation Samples for USA SubcontractorRead Article →
Articles · 1 min readDemolition Estimation ServicesRead Article →
Articles · 3 min readPlumbing Estimation SamplesRead Article →
Articles · 3 min readDivision 10 Specialties Estimation SamplesRead Article →Get a Bid-Ready Estimate in 24–48 Hours
Send your drawings and bid date. We'll confirm scope, price and delivery time before any work starts.

I recently worked with Design Estimation for electrical estimation on one of my projects, and I am extremely impressed with their professionalism and accuracy. From the very beginning, their team showed a deep understanding of the scope and provided a detailed, well-structured estimate that helped me plan with confidence.
The breakdown of material, labor, and costs was transparent and easy to follow, which gave me peace of mind that nothing was overlooked. They were also very responsive to my questions and delivered the estimate on time without compromising on quality.
Thanks to their expertise, I was able to save both time and money by avoiding potential mistakes and delays. I highly recommend Design Estimation to anyone looking for reliable and precise electrical estimation services.
— Teddy Smith