Earthwork is measured in thousands of cubic yards, so small errors in grades or factors become large dollar amounts. This guide explains how earthwork is taken off and priced.
What an Earthwork Takeoff Includes
| Item | Unit |
|---|---|
| Clearing and grubbing | Acres or square feet |
| Topsoil stripping and stockpile | Cubic yards |
| Cut and fill | Cubic yards from grade comparison |
| Over-excavation and recompaction | Cubic yards, from the soils report |
| Import or export | Cubic yards, after swell and shrink |
| Utility trenching and backfill | Linear feet and cubic yards |
| Building pads and subgrade | Square feet and cubic yards |
| Erosion control | Linear feet and each |
Fill in your details and we’ll get back to you with a quote.
- Quote reply within 1 hour
- Estimates in 24–48 hours
- Prepared by human estimators
How Cut and Fill Is Calculated
- Build existing and proposed surfaces from the grading plan.
- Compare them with a grid, cross-section or 3D surface method.
- Subtract pavement and building sections to reach subgrade.
- Apply swell (cut expands when loose) and shrink (fill compacts) factors.
- Balance the site and calculate import or export.
Our cut and fill guide works through examples.
What Drives Earthwork Cost
- Soil type and rock.
- Groundwater and dewatering.
- Haul distance and truck access.
- Compaction requirements and testing.
- Weather and seasonal restrictions.
See our excavation cost guide and solar farm earthwork guide.
What You Receive
- Cut and fill volumes and balance.
- Quantities by activity.
- Equipment, labor and hauling estimates.
- Cut and fill maps and marked-up plans.
See our sitework estimating services or send your grading plans.
Earthwork Quantity Takeoff Tools
An earthwork quantity takeoff (or excavation quantity takeoff) is usually prepared with earthwork estimating programs that build 3D surfaces from grading plans and calculate cut, fill and mass haul. The software speeds up the math, but the estimator still sets subgrade depths, swell and shrink factors and the haul plan. See our soil swell and shrink guide and sitework estimating guide.
Share This Entry
Frequently Asked Questions
Quick answers to the questions contractors ask us most.
How is earthwork calculated?
By comparing existing and proposed grade surfaces to find cut and fill volumes, then adjusting for swell, shrink and subgrade.
What are swell and shrink factors?
Swell is the increase in volume when soil is excavated; shrink is the decrease when fill is compacted.
Do you include utility trenching?
Yes. Trenching, bedding and backfill are measured by utility and depth.
What do you need for an earthwork takeoff?
Grading plans with existing and proposed contours or surfaces, plus the soils report and site plan.
How long does an earthwork takeoff take?
Most earthwork takeoffs are delivered in 24 to 48 hours, depending on site size.
Are earthwork estimates prepared by AI or human estimators?
Our estimates are prepared and reviewed by experienced human estimators, with software used for surface modeling.
Related Articles
Articles · 7 min readCut and Fill Calculation: How to Estimate Earthwork VolumesRead Article →
Articles · 9 min readSolar Farm Earthwork Estimation & Takeoff: Pro Guide and TipsRead Article →
Articles · 4 min readSite Work Solid Foundations SampleRead Article →
Articles · 7 min readGovernment & Public Works Bidding: How to Win Without LosingRead Article →
Articles · 4 min readPainting Estimating and Takeoff Services for ContractorsRead Article →
Articles · 8 min readEstimating Service Agreements: How to Avoid Hidden Fees in Takeoff ContractsRead Article →Get a Bid-Ready Estimate in 24–48 Hours
Send your drawings and bid date. We'll confirm scope, price and delivery time before any work starts.